Process Id Activity Theme Details of work to be carried out Time Required in
days
A Base map Generation District wise Village map Join all taluka wise village maps and remove errors 0.5
mosaic (GVMP)
District wise Settlement Get settlement point from Cadastral map, Verify same with Census 2
point map (GVMP) record, Village polygon map (2001) and Settlement 2001
Road map (NRIS) Generate district wise network dataset, which useful for distance 1
measurement
Rail map (NRIS) Proposed to be used from existing database
Drainage (NRIS) Proposed to be used from existing database
B Health Department RH/ SH/ PHC/ Sub-centers about 1500 data entry per district and its validation 3
database - Data entry / Non-Standard institute
(Unani, Aurvedic,
Allopathic)
C Analysis (a) Buffer generation - 25 Taluka-wise Geo-processing based on buffers and distance will be
km, 20 km, 5 km carried out for a district
1
(b) Census-2001 analysis Taluka-wise – PHC-wise population analysis and summary report 2
and report generation generation
D Printout Generation Print out - A3 size 1) RH/ SH - District output 2
2) Taluka wise - PHC with buffer
3) Taluks wise sub-center with buffer
4) Taluka wise PHC with non standard institutes
5) Population 2001 data
6) Distance to each heat 12
Man days per district
Total 33 districts = total mandays 396